2004-5 Pipe

 

Home

Projects

Background

2004 07 27 Heavy Rain

2004 08 30 Tropical Storm Gaston

Day 1 - Our Sandbox Toys are Bigger than Yours

Sandbox toys, day 3

Sandbox toys, day 4

Sandbox toys, 2004 12 22

Sandbox Toys, 2004 12 28

2004 12 29, More Cutting

2004 12 30 Second Cut, Headwall Starts

2005 01 03 Sandbox Toys

2005 01 04 Pipe Install

2005 01 05 Pipe Install

2005 01 06 Pipe Install

2005 01 07 Pipe Install

2005 01 10 Pipe Install

2005 01 11 Pipe Install

2005 01 12 Pipe Install

2005 01 13 Pipe Install

2005 01 17 Pipe Install, Last Sections

2005 01 18 Riprap In, Old Pipe Out

2005 01 19 Riprap In, Headwall Dig, Snow

2005 01 21 Headwall Pour Starts

2005 01 24 Headwall Forms Work

2005 01 25 Headwall Forms Work

2005 01 26 Headwall Forms Work, Headwall Poured

2005 01 27, Riprap, Drive Repaired

2005 01 28, Headwall Finished

2005 04 02 It Works

2005 04 15, Last Riprap, Grading

2005 04 18 Grout, Topsoil, Grading

2005 04 19 Topsoil, Grading, Grass

 

 

2005 01 04 Pipe Install

Prev Next

Today a few pipe sections were installed, but best of all, those pipe sections went through the now buried dam. That part of this project is now in the past. The forms were also taken off the headwall wings and that structure was finished.

Here's what the opening in the dam looks like when cleaned up.

The concrete at the bottom of the dam looked like it might be a problem, but it turned out that the pipe would clear that with about two inches to spare. Good thing. Nobody was in the mood for more fooling around with this. The contractor uses very accurate laser sighting gadgets to determine elevations and grades, so they were confident of this fit, and they were right.

Here are a couple of shots of pipe being laid through and past the cut in the dam.

Seeing this progress after being stalled for a week getting through that dam was quite nice. Things should move relatively quickly now.

You can see the old pipe in a couple of the above shots. All they have to do is whack it once with the bucket on the excavator and it's smashed into little bits and they can bury it. Good.

The other major accomplishment today was getting the forms off the headwall structure at the tail end of the pipe. This was then finished off and cleaned up and looks good. I knew already that a storm like Gaston would fill this pipe, but I did not know until today that the water velocity at the tail of this pipe in such a storm would be 20 feet per second. That's fast, and a tube of water 5 feet in diameter moving that fast would have a lot of energy.

These guys that built the headwall were really good, and really fast. They has the forms taken down, the concrete all cleaned and surfaced, and they were cleaned up and gone in about 6 hours.

Prev Next